December 2024

Dear Audrey Purchaser,

We are pleased to report the following works at the Audrey Construction Site:

  • Bored piers and shotcrete walls are now complete.
  • Lift pits are being poured this week.
  • Excavation will also be completed by the end of this week.
  • Before the year concludes, the team will commence basement services penetrations and column footings.